Family Courtyard

Updated Thurs 12 May

Tiling

With the weather more favourable, work on tiling the courtyard areas around the family houses (F, G and H Blocks) has recommenced. Noise will be kept to a minimum and some minor disruption to access routes may occur from time to time.

Forecourt Resurfacing Work

Work to remove the existing concrete decking from the forecourt of G and H Block is urgently required to prevent further leaks affecting the underground carparks, Maintenance workshops and Nursery below. Removing the existing surface will be considerably noisy as requires the concrete to be drilled or scraped; the waterproofing and tiling will be less disruptive following this. The forecourt resurfacing work is scheduled to start on the 25th of July 2022 and should take between 4 and 5 weeks to complete.

Download the family forecourt timeline here.

Dates are indicative and may be subject to change as work progresses.